Build the programme by gates
Use measurable release points rather than one delivery date copied into every email.
- Scope and drawing review
- Stone, range and finish approval
- Model, sample or first-article approval
- Batch production and inspection
- Packing, booking and shipment
Identify the variables that change duration
Block availability, drawing maturity, repeated versus unique pieces, carving depth, test requirements, colour-range decisions, client response time, factory loading and destination logistics can all alter the critical path.
Control changes without hiding delay
Record the drawing revision, decision owner and effect on cost and programme for every change. An updated milestone schedule is more useful than preserving an obsolete promised date.